Skip to main content
Home

Contact us

  • Home
  • About us
    • Our people
    • Our Clients
    • Our community
    • Our Accreditations
    • Case Studies
    • Project Milestones
    • Our Work in Living Environments (Flipbook)
    • Our Work in Learning Environments (Flipbook)
    • Our Work in Caring Environments (Flipbook)
  • Services
    • Construction
    • Facilities Management
    • Housing Maintenance
    • Refurbishment Projects
  • News
  • Sectors
    • Housing
    • Schools and Academies
    • Colleges and Universities
    • Health and Care
    • Leisure
    • Heritage
    • Local Government
    • Business & Industry
  • Careers
  • Case Studies
  • Contact
  • Track my job
Menu

Breadcrumb

  • You are here:
  • Home
  • Bordon Mixed-use Care Facility
Bordon Mixed-use Care Facility

Bordon Mixed-use Care Facility

Bordon Mixed-use Care Facility

Mountjoy was appointed to deliver the construction of a new care home in Bordon on a vacant site. The building is to be occupied and managed by Omega Elifar Ltd who provide who provide specialist care for people with learning disabilities in Hampshire and Surrey.

The new facility will include an 8 bed full time care unit, a 10 bed independent living unit with communal facilities, including a hydrotherapy pool, sensory room, activity room and offices. A kitchen and dining room will be created with communal lounges, lift services and a car park. 

  • 2017
  • Pre-start site
    08 March 2017
    Pre-start site

    The vacant site before works began

  • Hoarding erected
    18 June 2017
    Hoarding erected

    To keep the site secure and due to its location on a busy road, Mountjoy commissioned bespoke hoarding to advertise the project and local employment opportunities.

  • Structural steelwork erected
    22 June 2017
    Structural steelwork erected

    A crane drops in the first structural steel beams that will be the main frame for the building

  • Lot 1 - Independent Living Units
    07 August 2017
    Lot 1 - Independent Living Units

    Steel frame with beam and block flooring, first floor construction seen above.

  • Lot 3 - Substructure
    07 August 2017
    Lot 3 - Substructure

    Substructure built for Lot 3 ready for beam and block and drainage

  • Metsec Stage
    05 October 2017
    Metsec Stage

    Lot 1 Ground Floor Metsec installed including render backing board.

  • Roof structure in progress
    27 October 2017
    Roof structure in progress

    Main body of building, concrete floor complete and roof structure in progress with half of fire proof painting complete.

  • Window installation
    27 October 2017
    Window installation

    The windows are now being installed as the building begins to take its final shape.

  • Roof Coverings
    03 November 2017
    Roof Coverings

    Installation of roof coverings to get the building watertight before winter.

  • Elevations
    10 November 2017
    Elevations

    Walls and windows are nearing completion on one block.

  • 2018
  • Taking Shape
    05 February 2018
    Taking Shape

    The two lots are really beginning to take shape now externally with cladding underway.

  • Internal works
    05 February 2018
    Internal works

    Internal stud work is up and its boarding has begun. The final floor is being screeded with underfloor heating complete.

  • Internal Decorations
    26 February 2018
    Internal decorations

    Now that the stud work is up, the walls are being skimmed and drying ready for decorating.

  • Cladding
    23 April 2018
    Cladding

    The cedar cladding is now being applied to the exterior of the buildings.

  • Cladding Completion
    16 June 2018
    Cladding Completion

    Completion of the cedar cladding to the buildings.

  • Installation of fixtures and fittings
    22 July 2018
    Installation of fixtures and fittings

    Residents rooms are fitted out with their wetrooms, kitchens, washing machines and other appliances.

  • Completion of the hydrotherapy pool
    24 July 2018
    Completion of the hydrotherapy pool

    Following of the installation of the hoist, safety systems and the setting of the pool, it is now filled and ready to use.

  • Room fit-outs
    10 August 2018
    Room fit-outs

    Furnishings and final touches added to kitchens and living spaces.

  • Readying for occupation
    10 August 2018
    Readying for occupation

    Final touches of interior decoration complete rooms for residents to occupy.

  • Building Handover

    Fifteen months later the new Lavender Hills care home is complete and handed over to Omega Elifar for their new residents and support staff.

About Us

  • Our People
  • Our Clients
  • Our Community
  • Our Accreditations
  • Case Studies
  • Project Milestones

Services

  • Construction
  • Facilities Management
  • Housing Maintenance
  • Refurbishment Projects

Sectors

  • Housing
  • Schools and Academies
  • Colleges and Universities
  • Health and Care
  • Leisure
  • Heritage
  • Local Government
  • Business & Industry

Follow us

Footer menu

  • Track my job
  • People System Login
  • Engage Login
  • Terms & Conditions
  • Liability Policies
  • Modern Slavery Act
  • Pay Gap Reporting
  • Privacy Policy

© 2021 Mountjoy. All rights reserved. | Website by Oyster Design

Cookie Settings
  • Home
  • About us
    • Our people
    • Our Clients
    • Our community
    • Our Accreditations
    • Case Studies
    • Project Milestones
    • Our Work in Living Environments (Flipbook)
    • Our Work in Learning Environments (Flipbook)
    • Our Work in Caring Environments (Flipbook)
  • Services
    • Construction
    • Facilities Management
    • Housing Maintenance
    • Refurbishment Projects
  • News
  • Sectors
    • Housing
    • Schools and Academies
    • Colleges and Universities
    • Health and Care
    • Leisure
    • Heritage
    • Local Government
    • Business & Industry
  • Careers
  • Case Studies
  • Contact
  • Track my job